The invention belongs to the technical field of optical cable laying, and provides a comprehensive cable channel circulating
relay type optical cable traction laying method, which comprises the following steps of: S1, preparing two
pipe penetrating devices with special lengths and two corresponding teams of workers, namely a
pipe penetrating device A and a team A, and a
pipe penetrating device B and a team B; s2, the cover plate above the channel is uncovered according to the head-to-
tail distance of the total length of the pipe penetrating device to form a
skylight, and meanwhile, the cover plate is uncovered in the optical cable laying direction circularly according to the distance; and step S3, the A team and the B team are simultaneously provided with the A pipe penetrating device and the B pipe penetrating device, and the A team enables the head end of the A pipe penetrating device to penetrate from the first
skylight and pushes the head end towards the optical cable laying direction. Cyclic
relay traction is carried out on the optical cable through the specially-made pipe penetrating device so as to realize uninterrupted continuous laying, the process is rigorous, the division of labor is clear, the working time is reasonably utilized, additional
power equipment is not needed, physical activities of workers are more convenient, the working efficiency is higher, the construction cost is lower, and idle work is completely eradicated.