Patents
Literature
Patsnap Copilot is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Patsnap Copilot

374 results about "Brickwork" patented technology

Brickwork is masonry produced by a bricklayer, using bricks and mortar. Typically, rows of bricks—called courses— are laid on top of one another to build up a structure such as a brick wall. Bricks may be differentiated from blocks by size. For example, in the UK a brick is defined as a unit having dimensions less than 337.5x225x112.5mm and a block is defined as a unit having one or more dimensions greater than the largest possible brick.

Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure

ActiveCN102116061AImprove flatnessImprove verticality qualityWallsEconomic benefitsRebar
The invention relates to a masonry construction method for filling a wall core pillar, a core girder and building blocks into a framework structure. The method comprises the following steps of: construction preparation, masonry installation, synchronous inspection and puttying according to the condition of the wall surface of brickwork, wherein in the masonry installation step, a construction mode of the core pillar and the core girder is described; the hollow part of a small concrete hollow building block is used for substituting a construction pillar ring and an intel template, so the problems caused by template construction are avoided; during construction, concrete hollow building blocks, light-weight solid building blocks and U-shaped concrete building blocks which meet the national building standard atlas are adopted to build a wall body; according to a preset position, steel bars of the core pillar and the core girder are connected with an original structural layer according toa designed specification and a required quantity of embedded bars; the concrete hollow building blocks are put into the steel bars; and after the mortar of the building body reaches a certain intensity, concrete is poured into holes so as to form a firm whole together with the wall body to achieve a very ideal effect. By the method, a very good economic benefit is achieved, and a wide social favorable comment is obtained.
Owner:中铁建工集团装饰工程有限公司 +1

Automatic offline stacking production line

ActiveCN105947686AArrangement requirements are simpleDoes not affect productionStacking articlesProduction lineBrickwork
The invention provides an automatic offline stacking production line. The automatic offline stacking production line comprises a first conveying line, a second conveying line, clamping board devices, a third conveying line, a first brick pushing mechanism, a first brick placing board, a second brick placing board, a second brick pushing mechanism, a fourth conveying line and a stacking device, wherein the first conveying line conveys a whole stack of board bricks; the second conveying line conveys single board bricks; the clamping board devices are positioned at the first conveying line and the second conveying line and are used for clamping and releasing the single board bricks; the third conveying line is connected with the second conveying line and supporting boards are stacked on the third conveying line and are conveyed by the third conveying line; the first brick pushing mechanism is positioned at the second conveying line and separates brick bodies from the supporting boards; the first brick placing board is used for collecting the brick bodies of the first brick pushing mechanism; the second brick placing board is positioned beside the first brick placing board and is used for collecting the brick bodies on the first brick placing board; the second brick pushing mechanism is positioned at the second brick placing board; the fourth conveying line is positioned on one side of the second brick placing board and conveys a stack of brick bodies out; and the stacking device clamps the brick bodies from the second brick placing board and places the brick bodies on the fourth conveying line. Compared with the prior art, the automatic offline stacking production line has the advantages that a whole technological process is not associated with a brickwork production line, offline stacking and assembling stacking are realized, brick stacks with various sizes can be stacked, the application range is wide, and the production efficiency is high.
Owner:FUJIAN QUNFENG MACHINERY

Method and structure for enhancing brickwork structure and improving earthquake resistant performance of structure by using carbon fiber

InactiveCN101672110AImprove the state of stressAvoid sudden destructionBuilding repairsFiberCarbon fibers
The invention relates to a method and a structure for enhancing a brickwork structure and improving earthquake resistant performance of the structure by using carbon fiber. The method comprises the following steps of: step one, determining a part to be enhanced and reconstructed and pre-treating the surfaces of a brickwork; step two, coating binder on the surfaces of the brickwork; step three, sticking carbon fiber cloth tapes on the surfaces of the brickwork in a gridding shape and in a double-surface symmetrical manner; step four, drilling a through hole; step five, using a carbon fiber pinto pass through the through hole, infusing glue in the through hole and sticking the carbon fiber pin with the brickwork; step six, dispersing the two ends of the carbon fiber pin which are exposed from the brickwork in a strip shape, and respectively sticking and fixing the two ends with the carbon fiber cloth tapes on the two surfaces of the brickwork in a petal shape; and step seven, additionally sticking a piece of glue-coated carbon fiber cloth in an each area in which strips are stuck. The method solves the technical problem that the carbon fiber cloth tapes on the two surfaces of the brickwork lack organic linkage and can not ensure the cooperative work of the carbon fiber cloth tapes and the brickwork structure. The adoption of the method can effectively enhance the whole earthquake resistant performance of the brickwork structure. Meanwhile, the method also has the advantages of simple and convenient construction, short construction period, no original space occupation, no load added to the structure or a foundation and low investment.
Owner:BEIJING ZHUFU ARCHITECTURE AFFAIRS CO LTD

Construction method of walling and filling combined gob-side entry retaining wall body

The invention relates to a construction method of a walling and filling combined gob-side entry retaining wall body. The construction method comprises the following steps of: closely following forward propulsion of a stope face, erecting dense single supports at a gob retaining side at the rear part of a fully mechanized mining bracket, so that a space of a tunnel at the rear part of the stope face is retained; walling a square template wall with concrete pier blocks under the mask of the dense single props; meanwhile, installing counter-pulled anchor rods which penetrate through the template wall bodies, and carrying out lateral reinforcing on the template wall bodies; carrying out grouting filling on a hollow part defined by the template walls through injected holes reserved on the template walls till the internal spaces of the template walls are filled with grout; carrying out uniform whitewashing treatment on the wall at one side of a gob retaining tunnel to form a concrete spray layer; and sequentially circulating the steps along with propulsion of the stope face till construction of the whole gob-side entry retaining wall body is finished. According to the construction method disclosed by the invention, a brickwork wall and a filling support are combined together, so that the construction method is simple and convenient and simple to operate and ensures that the wall body has high strength and can yield pressure suitably; and length of each walling of the wall body is consistent with the everyday propulsion degree of the stope face, and the construction method is flexibly suitable for actual mining.
Owner:CHINA UNIV OF MINING & TECH

Anti-seismic reinforcing structure and method of old brickwork building

ActiveCN102003080AGood seismic reinforcement systemMeet planning requirementsBuilding repairsProtective buildings/sheltersFloor slabLife quality
The invention relates to an anti-seismic reinforcing structure and a method of an old brickwork building. Sheathed prefabricated structures are respectively arranged at two sides of the old brickwork building to anti-seismically reinforce the old brickwork building and the inner sides of the sheathed prefabricated structures are connected with the outer longitudinal wall of the old brickwork building; a roof straining beam is arranged on the roof and the sheathed prefabricated structures at the two sides are fixedly connected into a whole through the roof straining beam; the reinforcing structure consists of the sheathed prefabricated structures at the two sides and the roof straining beam; and the sheathed prefabricated structures respectively comprise a newly added longitudinal wallboard, a newly added transverse wallboard, a newly added floor and a roof straining beam. The anti-seismic reinforcing structure has reliable anti-seismic performance, and can ensure that the residents are unnecessary to move and the construction is carried out outdoor during the reinforcing construction; the constructional members are machined in a prefabrication way, therefore, the site construction time is short, the wet operation volume is small, the quantity of construction templates is less, and the work noise at the construction site is low; moreover, the anti-seismic reinforcing aim of the old building and the using condition improving aims are skillfully combined, thereby increasing the usable area and improving the life quality of the residents.
Owner:BEIJING INST OF ARCHITECTURAL DESIGN

Blast furnace brickwork slag shell thickness monitoring system and method

The invention relates to a blast furnace brickwork slag shell thickness monitoring system and method and belongs to the technical field of blast furnace monitoring. The system comprises a background processing system and a client system, wherein the background processing system comprises a data acquisition module, a data validity judgment module, a cooling water temperature calculating module, a cooling water heat transfer coefficient calculating module, a thermal load calculating module and a slag shell thickness calculating module; the client system comprises a slag shell monitoring and calculating parameter setting module, a slag shell timing sequence thickness display module, a slag shell real-time thickness display module and a brickwork thickness alarm processing module. The method comprises the following steps: determining the characteristics of brickwork heat transfer, calculating the temperature and the heat transfer coefficient of cooling water, calculating the quantity of heat taken away by the cooling water, calculating the heat quantity transferred from the interior of a blast furnace to the hot surface of the wall body of a cooling wall, and establishing the relational expression of calculating the slag shell thickness. According to the system and method, an objective and quantized basis is provided for knowing the brickwork slag shell condition during the blast furnace smelting process, a blast furnace operator is helped to timely know the condition of the brickwork, so that reasonable operating measures are taken, the stable operation of the blast furnace is ensured, and the service life of the blast furnace is prolonged.
Owner:CISDI ENG CO LTD

Building brickwork and masonry construction method of building brickwork

InactiveCN104358341AMeet the requirements of self-insulation systemSolve common quality problemsConstruction materialWallsMaterials scienceConcrete composites
The invention discloses a building brickwork and a masonry construction method of the building brickwork, and relates to a building brickwork of a building. The building brickwork is a brickwork which is built by light-weight aggregate concrete composite blocks; grooves and tongues are formed in the periphery of each light-weight aggregate concrete composite block; the light-weight aggregate concrete composite blocks are respectively 600-1200mm in length, 300-600mm in height and 80-200mm in thickness; the grooves are downward and the tongues are upward in field masonry; and the masonry construction method comprises the following steps: (1) building the brickwork by the blocks, namely building the first block on a foundation or floor ground, building the second composite block in a manner of being staggered with the first block, wherein the staggered-joint is 1/2 of the length of the block and is not smaller than 200mm at least; the composite block brickwork is connected with a building structure column and a concrete shear wall; the composite block brickwork is connected with building structure beams and plates; the building brickwork is subjected to deformation joint construction; a parapet wall is subjected to masonry construction; a switch socket is pre-buried and installed; and cable pipelines are laid; (2) fixing door frames and window frames; and (3) building a wall body corner structure by the light-weight aggregate concrete composite blocks.
Owner:FUJIAN MEIJINLAI GREEN BUILDING TECH +1

Deformation-controllable frame filling wall and construction method thereof

The invention discloses a deformation-controllable frame filling wall which is mainly composed of a frame 1, a filling wall 2, deformation control parts 3, horizontal tie bars 4, restraint columns 5 and horizontal connection beams 12. The deformation-controllable frame filling wall is characterized in that the frame 1 is composed of a frame upper beam 6, a frame lower beam 7, a frame left column 8 and a frame right column 9, the filling wall 2 is a brickwork filling wall which is built by bricks (clay bricks and hollow bricks) or concrete building blocks, the deformation control parts 3 are arranged at positions where four corners of the filling wall contact with joints of the frame, the filling wall 2 is connected with the frame left column 8 and the frame left column 9 through a flexible material 10, and connected with the frame upper beam 6 and the frame lower beam 7 through an elastic connection material 15, the restraint columns 5 are arranged at positions where the filling wall 2 is connected with the flexible material 10, and the horizontal tie bars 4 which are arranged in the height direction of the filling wall are connected with the restraint columns. When the height of the filling wall is large, horizontal tie beams 12 can be arranged in the filling wall, and two ends of the horizontal tie beams 12 are connected with the restraint columns 5.
Owner:INST OF ENG MECHANICS CHINA EARTHQUAKE ADMINISTRATION

Detection method for detecting brickwork shear strength of cement mortar concrete porous brick wall

The invention discloses a detection method for detecting the brickwork shear strength of a cement mortar concrete porous brick wall. According to the method, the brickwork shear strength is detected based on the core drilling method. The brickwork is directly drilled to obtain a core sample. Arc surface-shaped holes in the core sample of the porous brickwork are filled densely by adopting the quick-hardening material. Meanwhile, the end bearing surface of the core sample is leveled and blocked up. After that, the shear strength test on the brickwork is conducted along the straight-joint cross section of the core sample. The shear strength of the brickwork core sample is converted into the shear strength of the brickwork. According to the technical scheme of the invention, the detection result of the method directly reflects the shear strength value the straight-joint cross section of the brickwork, so that the shear strength of the brickwork can be accurately reflected. Therefore, the method provides a basis for design-checking and calculation or identification and reinforcement. Meanwhile, the result is accurate and reliable, and the damage to the original structure is reduced, wherein a damaged part can be easily repaired. The above technique completes the field detection technology of brickwork projects and has good social and economic benefits. The correlation index of a relation curve between the shear strength of the core sample and the shear strength of a brickwork standard component is relatively high, and the average relative error of the curve is 13.7%. The relative standard deviation of the curve is 19.7%.
Owner:SICHUAN INSITITUTE OF BUILDING RES

Low-resistance anti-block vertical flow wetland structure

The invention relates to a low-resistance anti-blockage vertical flow wetland structure. A rectangular pressure-bearing pool (20 to 30 meters deep and unlimited in length and depth) is parallelly divided into a water distribution ditch, a filling basin and a water collecting ditch by two separating pool ridges, wherein the separating pool ridge between the filling basin and the water collecting ditch is 300 millimeters lower than the other poll ridge and is uniformly distributed with 'V'-shaped weirs on the top, and the water distribution ditch and the water collecting ditch are communicated with adjacent process units through a water inlet and a water outlet; water distribution pipes are parallelly arranged at the bottom of the filling basin at 500 millimeter intervals on a plane at a height of 30 millimeters, the water inlet ends of the water distribution pipes pass through one separating pool ridge to be exposed in the water distribution ditch, the other ends of the water distribution pipes pass through the other separating pool ridge to be exposed in the water collecting ditch and are blocked by plugs with threaded-openings, and the water distribution pipes are provided with dense water outlet holes and are protected by a dry brickwork outer shell; a filling is filled in the filling basin to a level 100 to 150 millimeters lower than the 'V'-shaped wires, water is filled into the filling basin, plants are planted in the filling basin and the filling basin is put into operation; and water flow from the prior process unit first enters the water distribution ditch through the water inlet, then enters the water distribution pipes from the water distribution ditch, later on overcomes the resistance of the water outlet holes on the water distribution pipes to enter a filling layer, rises slowly at a constant and low speed from the filling layer to a free water layer above the filling layer, overflows from the 'V'-shaped wires and falls into the water collection ditch.
Owner:NANJING INST OF GEOGRAPHY & LIMNOLOGY

Method for computer simulation of installation construction of oven protection equipment of coke oven

The invention relates to a method for the pre-installation construction of the oven protection equipment of a coke oven, in particular to a method for the computer simulation of the installation construction of the oven protection equipment of a coke oven, which comprises building an analysis module, a computing module, a structure design module and a drawing module, wherein the analysis module receives in-situ equipment test data input by a terminal user; the computing module computes the qualification rate of equipment data in sampling inspection; the structure design module has a built-in equipment general assembly and several sub assemblies formed by subdividing the entire oven protection equipment of the coke oven, and according to an assembly model selected by a user, and the system assigns acquired equipment dimension data values to the assemblies to obtain a three-dimensional entity and installation deviations between different sets of equipment and between equipment and a brickwork and simulate the installation process of the oven protection equipment to obtain a relative position of the equipment during installation; and the drawing module outputs the distribution condition of the installed entity and a model of the entity. The invention overcome the drawbacks, such as complex construction, long time consumption, and human, money and material resource waste, of the traditional assembly method.
Owner:CHINA 22MCC GROUP CORP

Homogeneous same-phase silica mud for large coke oven

ActiveCN102992784AVolume effect stabilityConsistent thermal expansionCarboxymethyl celluloseGranularity
The invention discloses a homogeneous same-phase silica mud for a large coke oven, which comprises the following components in parts by weight: 70-80 parts of waste silica bricks with SiO2 content higher than 94%, 17-25 parts of natural silica with SiO2 content higher than 98%, 2-5 parts of soft binding clay with Al2O3 content higher than 25%, 0.05-0.1 part of carboxymethyl cellulose, 0.1-0.2 part of white dextrin, 0.1-0.2 part of medium-temperature sintering agent sodium carbonate and 0.1-0.2 part of high-molecular polymer polyacrylamide. The homogeneous same-phase silica mud according to claim 1 comprises the granularity of the waste silica bricks comprises the following parts in parts by weight: 23-25 parts of 1-0.5mm waste silica bricks, 15-16 parts of 0.5-0.2 mm waste silica bricks, 8-10 parts of 0.2-0mm waste silica bricks, 13-15 parts of 180-mesh waste silica bricks and 11-14 parts of 220-mesh waste silica bricks. The homogeneous same-phase silica mud for the large coke oven according to claim 1 is characterized in that the sieving rate for the soft binding clay to pass through a 180-mesh sieve is bigger than 95%. A preparation method for the homogeneous same-phase silica mud according to claim 1 comprises the following steps: 1, preparing and adding 70-80 parts of waste silica bricks, 17-25 parts of natural silica, 2-5 parts of soft binding clay, 0.05-0.1 part of carboxymethyl cellulose, 0.1-0.2 part of white dextrin, 0.1-0.2 part of medium-temperature sintering agent sodium carbonate and 0.1-0.2 part of high-molecular polymer polyacrylamide to a double-helix mixing mill for pre-mixing; 2, packaging the mixed material based on piece weight; 3, adding the silica mud to a sand mixer at a using site, and directly adding the silica mud to the sand mixer, adding tap water which is 30-35% of the total weight of the silica mud for stirring for 10-15 minutes, and stewing the mixture for 30 minutes; and 4, directly coating the mixed materials to a brickwork for use.
Owner:REFRACTORY MATERIAL OF SINOSTEEL CORP

Building process of furnace bottom of electric furnace

The invention relates to the building process in metallurgical field and provides a building process of a furnace bottom of an electric furnace. The process comprises the following steps: examining the roundness of a furnace bottom and a furnace shell, confirming that the furnace shell has no obvious deformation and cleaning off slag adhesion and ash deposition in the furnace shell so as to ensure an air hole unblocked, coating a layer of glue evenly; at the junction of the furnace bottom and the furnace wall, pasting two layers of nano material reflective heat insulating boards layer by layer in the direction of the furnace bottom, wherein the reflective heat insulating boards are used as a heat insulating material layer, the thickness of each layer of reflective heat insulating board is5mm, the nano material reflective heat insulating boards need to be pasted flatly, solidly and orderly without cavities, joints of the two nano reflective heat insulating boards need to be staggered;flatly laying two layers of magnesite bricks above the heat insulating material layer, and filling brickwork joints with fine magnesite, wherein each layer of magnesite brick is 76mm thick; laying a layer of magnesia carbon bricks with the tickness of 150mm, and filling brickwork joints with fine magnesite; paving bottom ramming material with the thickness of 650mm above the magnesia carbon bricks, and ramming the bottom ramming materials by a ramming machine to ensure the surface fastness and form a pot-bottom-shaped furnace bottom. The process provided by the invention can ensure controllable reaction between carbon and oxygen, increase a furnace heath and improve the heat insulation effect of the furnace bottom of an arc furnace.
Owner:NANJING IRON & STEEL CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products