The invention belongs to the technical field of high-temperature pipeline installation, and particularly relates to a high-temperature pipeline cold-state pre-stretching installation method which comprises the following steps: S1, cold-state pre-stretching stress calculation; s2, on-site
anchor point condition confirmation; s3, preparation before construction; s4, measuring and
cutting at a pre-stretching
pipe orifice; s5, the lifting lug and the guide plate are welded; s6, cold-state pre-stretching is conducted, and welded junctions are assembled; s7, reinforcing the welded junction of the pipeline and dismantling the pre-tensioning device; s8, formally
welding a pipeline
welding seam; and S9,
nondestructive testing is conducted, and reinforcing facilities are dismantled. Pretension force is applied to the pipeline in advance, so that deformation of the pipeline in a
thermal state can be controlled to a certain degree, thrust and torque of the pipeline to equipment are reduced, the
stress level of the pipeline is reduced, safety and reliability of the pipeline are improved, meanwhile, use of expansion joints and compensators is reduced, and the production cost of enterprises is effectively reduced; and moreover, the device can be suitable for construction sites with compact spaces, the construction difficulty is effectively reduced, and the construction efficiency is improved.