Patents
Literature
Hiro is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Hiro

49results about How to "Avoid construction difficulty" patented technology

Integral Pushing Construction Method of Network Tied Arch Bridge

The invention relates to a guiding-beam-free integral thrusting construction method of a network tied arch bridge. The method is characterized in that the following structure and method are adopted for thrusting the network tied arch bridge: a vertical jack is arranged at the front end in the thrusting direction of a steel box tie beam; a sliding mechanism which can ensure a piston of the jack toslide on the top surfaces of temporary piers is arranged on the top surfaces of the temporary piers; during thrusting, when the front end of the arch bridge is close to the temporary piers, the piston of the jack moves downwards to push against the sliding mechanism and the height of the front end of the arch bridge relative to the top surfaces of the temporary piers is adjusted by controlling the extension elongation of the piston to ensure chutes at the bottom of the steel box tie beam to fall on pulleys; and the chutes are supported by the pulleys and slide relative to the pulleys along with thrusting movement of the arch bridge. The method has the following beneficial effects: in the thrusting process, a main arch ring, inclined hangers, the steel box tie beam, the temporary supports and the like are integrally thrust, thus giving play to the function of partial inclined hangers to enhance the structural rigidity in the thrusting process, simultaneously avoiding installation inconvenience and construction difficulty after the members are thrust in place and improving the thrusting construction efficiency.
Owner:CHANGSHA UNIVERSITY OF SCIENCE AND TECHNOLOGY

High-altitude large-cantilever concrete structure structural steel supporting platform

The invention relates to a high-altitude large-cantilever concrete structure structural steel supporting platform. The high-altitude large-cantilever concrete structure structural steel supporting platform comprises a multi-truss structural steel triangular supporting bracket, a box iron horizontal connecting beam and a plurality of box iron horizontal purlines. The multi-truss structural steel triangular supporting bracket comprises a main beam, a horizontal rod, a vertical rod, a first inclined supporting rod and a second inclined supporting rod. The main beam is installed on a boundary beam of a frame structure on the next layer of a cantilever structure needing to be constructed, the first inclined supporting rod and the second inclined supporting rod are installed on a boundary beam of a frame structure on the next second layer and a boundary beam of a frame structure on the next third layer of the cantilever structure needing to be constructed respectively, the horizontal rod is connected with the first inclined supporting rod and the second inclined supporting rod, the joint of the second inclined supporting rod and the horizontal rod is connected with one end of the vertical rod, the other end of the vertical rod is connected with the main beam, the box iron horizontal purlines are welded to the upper surface of the main beam in a laying mode and are used for erecting a formwork support and an external scaffold, and multi-truss structural steel triangular supporting brackets are connected through box iron horizontal connecting beams in a welding mode. The high-altitude large-cantilever concrete structure structural steel supporting platform solves the problem that the construction difficulty of an ultrahigh and large-cantilever structure with large component loads is high.
Owner:SHANGHAI ZHONGJIN CONSTR GRP

Drill absorption pile structure and construction method thereof

The invention relates to an offshore drilled absorbing pile and the construction method thereof. When a drilling bit (11) breaks the ground and is drilled, an immersed tube is drilled into a high pressure water pump (18) on the main machine of a drilling machine, and supplies high pressure water for the lower part of the drilling bit through the central tube of a drilling rod to form high pressure slurry, and the slurry is discharged out of the drilled absorbing pile through a one-way valve (7) installed on a baffle plate and a slurry discharging tube (9) connected with the one-way valve. The drilling bit is drilled and breaks the ground from the upper part of the sealed bin of the drilled absorbing pile to the bottom of the drilled absorbing pile to clean all the soil plugs in the sealed bin out of the drilled absorbing pile, the drilling bit is stopped, and simultaneously the high pressure water pump (18) stops supplying water. A submersible sewage pump on the drilling machine is started up, the one-way valve (7) on the cone shaped baffle plate is closed to ensure that a sealed space is formed at the lower part, the sea water is discharged from the sealed space through the submersible sewage pump (19) to form negative pressure, the drilled absorbing pile is immersed into the sea bed under the sea water pressure, the drilling bit is supported on the mud surface and keeps still when the drilled absorbing pile is immersed, the cone shaped baffle plate of the drilled absorbing pile is lowered to the drilling bit position along the drilling rod (10) to stop the water discharging of the submersible sewage pump, and thus the primary drilling of the drilled absorbing pile is completed. The former operations are repeated to ensure the drilled absorbing pile to enter into the sea bed in a step-by-step immersed tube drilling way, in order to complete the driving-in construction of the drilled absorbing pile.
Owner:天津市海恩海洋工程技术服务有限公司

Hybrid beam manufacturing device and manufacturing method

The invention provides a hybrid beam manufacturing device and manufacturing method. The hybrid beam manufacturing device comprises a template and a steel reinforcement cage; the template comprises analuminum alloy bottom board, aluminum alloy side boards, foam boards, heightened square pipes, strengthened square pipes, strengthened screw rods, nuts and strengthened backing boards; and the steel reinforcement cage comprises H-shaped steels, beam face reinforcements, beam bottom reinforcements, hoop reinforcements, beam waist reinforcements and tied reinforcements. The method comprises the following steps of protective layer reinforcement welding, steel reinforcement cage skeleton welding, steel reinforcement cage bandaging, die assembling, releasing agent brushing, steel reinforcement cagedie entering, hoisted embedded part mounting, template reinforcing, pouring and vibration, maintenance and die stripping. The hybrid beam manufacturing device and manufacturing method have the advantages that by using an aluminum template, the aluminum template can be recycled, and materials are saved; double advantages of a steel structure and a concrete structure are combined; the problem of collision of the reinforcements when a pure concrete beam component is mounted as well as the construction difficulty and the quality control difficulty caused by a great quantity of wet work in the field and the like are effectively avoided; and the hybrid beam manufacturing device and manufacturing method are suitable for large-scale production, simpleness, convenience and feasibility in technology and low manufacturing cost.
Owner:CHINA CONSTR SEVENTH ENG DIVISION CORP LTD +1

Incremental launching technology of submerged cable-stayed floating tunnel

The invention discloses incremental launching technology of a submerged cable-stayed floating tunnel. The incremental launching technology of the submerged cable-stayed floating tunnel comprises the following steps that all pipe joints of the submerged floating tunnel in a land area prefabrication yard are prefabricated, then the pipe joints are transported to an incremental launching side shore connecting structure through a land area slope tunnel, secondary outfitting is successively carried out, the pipe joints are docked with the subsequent pipe joints and sealed into water, then the pipejoints are in a receiving side shore connecting structure section by section in an incremental launching manner; stay cables are installed on the pipe joints one by one along with incremental launching and pulled to a stay cable anchorage pier; and after incremental launching is completed, concrete on the outer surface of the pipe joints at both ends of the submerged floating tunnel is poured intothe incremental launching side shore connecting structure and the receiving side shore connecting structure, the consolidation of the pipe joints at both ends of the submerged floating tunnel is completed, then the buoyant weight ratio can be adjusted by adjusting the ballast water volume in each pipe joint, and the cable force adjustment of the stay cable is carried out and the sealing anchor iscarried out at the stay cable anchorage pier. The incremental launching technology of the submerged cable-stayed floating tunnel has little influence by wind, wave, current, ship traveling wave and the like, greatly reduces the safety risk of man-machine for offshore construction, and has high construction efficiency and short construction period.
Owner:CCCC THIRD HARBOR ENG +1

Novel bolt-ball joint and preparation method thereof

The invention relates to a novel bolt-ball joint and a preparation method thereof, and belongs to the technical field of bolt-ball joint design. The novel bolt-ball joint comprises a steel ball and branch tubes, a cavity structure is arranged inside the steel ball, the branch tubes are arranged on the steel ball and used for connecting and bearing steel rods, the steel ball and the branch tubes are integrally formed, the steel ball is in the shape of a partially cut ball crown, the height of the ball crown is larger than the radius of the steel ball, the branch tubes with solid structures arearranged outwards along the normal direction of the steel ball and uniformly distributed along the circumferential direction of the steel ball, counter bored holes are formed in the branch tubes alongthe normal direction, fillet surfaces for smooth coherent transition of the adjacent branch tubes are arranged on the surface of the steel ball, the surface of the steel ball is in the shape of a curved surface calculated by topological optimization taking the number of the branch tubes, the positions of the branch tubes, the diameters of the branch tubes and the diameters of the counter bored holes as parameters, and the stress of the curved surface is matched with that of the borne steel rods. The bolt-ball is subjected to topological optimization analysis, so that the bolt-ball joint meetsbearing capability, the dead weight of the bolt-ball joint is greatly reduced, and service performance is improved.
Owner:HENAN UNIVERSITY

Assembly type joint of round-inside and square-outside compound steel structure type column, connection and generation method thereof

The invention discloses a assembly type joint of a round-inside and square-outside compound steel structure type column. The assembly type joint comprise a first joint connector and a second joint connector, the first joint connector comprises a first cross-shaped connecting panel which is connected with the lower end part of an upper side inner round steel pipe and a first sleeve connector whichis connected with the inner wall of the lower end part of an upper side outer square steel pipe, the second joint connector is consistent with the first joint connector in structure, and a first channel steel connector and a second channel steel connector are further included. Through reasonable arrangement of part structures, field welding and concrete operation are reduced, the construction quality is guaranteed, the construction speed is increased, and meanwhile the construction cost is saved; by the adoption of the assembly type splicing joint for the round-inside and square-outside hollowinterlayer type compound concrete-filled steel tubular column and the connecting method, assembly construction of a compound concrete-filled steel tubular structure can be achieved, and the buildingindustrialization process is accelerated; and meanwhile, a user does not need to manually carry out position selection and parameter setting on a connecting part, and then the column splicing joint required in design software can be automatically generated.
Owner:CHANGAN UNIV

Device for shield plane sliding stepping in narrow space and construction method thereof

The invention discloses a device for shield plane sliding stepping in a narrow space. The device comprises an arc-shaped guide table and a guide rail, and further comprises a force transmission mechanism connected with thrust cylinders on a shield main machine and an auxiliary force transmission mechanism positioned on the shield main machine and used for pulling the force transmission mechanism,wherein the force transmission mechanism comprises a plurality of force transmission blocks connected with one ends of the thrust cylinders, a cross beam connected with the force transmission blocks and counter-force supports positioned on one side of the cross beam; and the bottoms of the counter-force supports are connected with the arc-shaped guide table, and the number of the counter-force supports is equal to that of the thrust cylinders. The device is simple and practical, existing resources such as standard block segments are utilized, the steel structure arc-shaped guide table does notneed to be independently machined, and cost is saved; plane sliding is achieved in the small space, the section size of a sliding channel does not need to be increased, and the safety risk of a shallow buried section tunnel is reduced; and a supporting stress structure adopts the H-shaped steel cross beam to increase the supporting stress area, the cross beam and the counter-force supports transmit force in a balanced and symmetrical mode, operation is easy and convenient, and use is safe.
Owner:CHINA RAILWAY TUNNEL GROUP CO LTD

Construction method for reforming overall topography by determining elevations by adopting garden path foundation trench excavation

The invention discloses a construction method for reforming the overall topography by determining elevations by adopting garden path foundation trench excavation. The construction method is characterized by comprising the following steps: (1) accurately calibrating the garden construction range; (2) surveying the construction range, cleaning the surface and removing barriers; (3) equipping construction and measuring personnel and machinery; (4) carrying out construction measurement and setting out on the garden paths and determining the elevation of each construction site; (5) excavating garden path foundation trenches and splitting green plots; (6) measuring and setting out each green plot and determining the topography reforming elevation point; (7) balancing earthwork for the first time and transporting earthwork inward; (8) reforming the topography, namely making slopes or reshaping; (9) balancing earthwork for the second time and stacking, filling or transporting earthwork outward; (10) carrying out inspection and acceptance and follow-up treatment on the construction sites. The method for reforming the topography along the foundation trenches is adopted and has the beneficial effects that earthwork moving is reduced; the topography reforming cost is saved; the construction difficulty is reduced; the earthwork is stacked neatly; earth is filled conveniently; construction is carried out orderly; the construction progress can be accelerated; the manpower and material resources can be saved; the garden reforming efficiency and quality are improved.
Owner:FLOWER KING ECO ENG CO LTD

Cement fly ash foaming composite heat insulation material

The invention relates to a cement fly ash foaming composite heat insulation material, which comprises a cement fly ash foaming heat insulation outer layer, a sandwich composite layer and a cement fly ash foaming heat insulation inner layer, wherein the sandwich composite layer is positioned between the cement fly ash foaming heat insulation outer layer and the cement fly ash foaming heat insulation inner layer; the cement fly ash foaming heat insulation inner layer is connected with a building concrete body; and the sandwich composite layer is prepared from a polyphenyl board (ERS board), an extruded toluene board (XPS board), hard foam polyurethane and polyphenyl granular slurry. The heat insulation material has the advantages that: the problem that the fly ash of a power plant pollutes the environment is solved; the industrial waste is prepared into the building energy-saving heat insulation material so as to solve the problem of waste consumption for the state, save the energy and change waste into valuable; the heat insulation material is a multi-purpose energy-saving heat insulation material, and can be used for heat insulation of a building peripheral structure; and the construction difficulty is solved, and the construction quality is ensured.
Owner:WUHAN CHANGHONGWEI TECH

Construction method for underwater deeply-buried structure

PendingCN111576457AIncrease safety reserveAvoid sinking difficultiesCaissonsTerrainHydrometry
The invention discloses a construction method for an underwater deeply-buried structure. The technological process comprises the step I of selecting proper underwater excavation equipment that can reach in waters according to the project geological exploration data; the step 2 of resurveying an underwater terrain, and designing a proper underwater excavation method and an excavation step-slope form according to design drawings and geological and hydrological data; the step 3 of performing surveying and setting out over water, and installing excavation monitoring equipment on the excavation equipment; the step 4 of performing underwater stepped excavation, and implementing necessary construction of an auxiliary construction platform after completion of excavation; the step 5 of constructingsinking cofferdam, and regulating implantation to a design attitude; the step 6 of pouring sandwich concrete and bottoming concrete of the cofferdam, and finishing cofferdam construction; and the step 7 of pumping water for dry construction of an underwater structure. According to the construction method, underwater excavation is implemented firstly, and then a water-surrounding auxiliary structure is constructed, so that dry construction environment of the structure is ensured; and the underwater construction problem of the deeply-buried structure below a complex geological riverbed can be solved in a high-quality mode quickly, efficiently and safely.
Owner:SICHUAN ROAD & BRIDGE GRP

High-altitude large cantilever concrete structure steel support platform

The invention relates to a high-altitude large-cantilever concrete structure structural steel supporting platform. The high-altitude large-cantilever concrete structure structural steel supporting platform comprises a multi-truss structural steel triangular supporting bracket, a box iron horizontal connecting beam and a plurality of box iron horizontal purlines. The multi-truss structural steel triangular supporting bracket comprises a main beam, a horizontal rod, a vertical rod, a first inclined supporting rod and a second inclined supporting rod. The main beam is installed on a boundary beam of a frame structure on the next layer of a cantilever structure needing to be constructed, the first inclined supporting rod and the second inclined supporting rod are installed on a boundary beam of a frame structure on the next second layer and a boundary beam of a frame structure on the next third layer of the cantilever structure needing to be constructed respectively, the horizontal rod is connected with the first inclined supporting rod and the second inclined supporting rod, the joint of the second inclined supporting rod and the horizontal rod is connected with one end of the vertical rod, the other end of the vertical rod is connected with the main beam, the box iron horizontal purlines are welded to the upper surface of the main beam in a laying mode and are used for erecting a formwork support and an external scaffold, and multi-truss structural steel triangular supporting brackets are connected through box iron horizontal connecting beams in a welding mode. The high-altitude large-cantilever concrete structure structural steel supporting platform solves the problem that the construction difficulty of an ultrahigh and large-cantilever structure with large component loads is high.
Owner:SHANGHAI ZHONGJIN CONSTR GRP

An integrated deep water foundation and its construction method

This application relates to an integrated deep-water foundation and its construction method, and relates to the technical field of bridge deep-water foundations, including multiple suction single wells, multiple steel pipe columns, multiple bored piles and caps. The steel casing used for bored pile construction, and the steel pipe column and the single suction well are an integrated structure prepared in advance. After the drainage operation of the single suction well, the steel pipe column and the single suction well can sink to the design elevation. There is no need to erect a large jacket platform and carry out processes such as hoisting, turning over, and sinking of steel casings in the marine environment with harsh swell conditions, and the suction well base and steel pipe columns can participate in the stress of the deep water foundation during the bridge use stage Among them, the free length of the single pile can be effectively reduced, and the horizontal and vertical bearing capacity of the pile body can be improved. Therefore, the application can not only reduce the construction risk, difficulty and cost, but also shorten the construction period and improve the horizontal bearing capacity and vertical bearing capacity of the pile body.
Owner:CHINA MAJOR BRIDGE ENERGINEERING

Fire early warning method based on logarithmic inverse time limit principle

PendingCN114202875ASolve the difficulty of getting electricityHigh economy and practicalityEmergency protection detectionFire alarm electric actuationThermodynamicsElectrical current
The invention discloses a fire early warning method based on the logarithmic inverse time limit principle, and the method comprises the steps: collecting the load current of an operation line through the environment operation state and the parameters of a power supply cable; the real-time temperature rise of the current power supply cable is estimated, the current cable temperature is estimated according to the environment temperature, and when the temperature is higher than the safe operation level, a fire early warning prompt is given; and performing a thermal accumulation process on the real-time load current by applying a logarithmic discretization inverse time limit algorithm, tripping and starting a thermal reset timing process when the running limit of cable heating is reached, and forbidding the line to be switched on and put into operation before thermal reset zero clearing in the thermal accumulation process. According to the method, the temperature and the heat accumulation time of the running line cable can be quickly estimated and judged without depending on an external cable temperature sensor, the running safety of the power cable is guaranteed, fire accidents caused by cable overheating are avoided, and the life and property safety of people is guaranteed.
Owner:江苏业力科技有限公司

Concrete filling and pouring method for connecting upper column section and lower column section of prefabricated steel reinforced concrete column

The invention discloses a concrete filling and pouring method for connecting an upper column section and a lower column section of a prefabricated steel reinforced concrete column. The method is characterized in that filament sleeves and lug plates are used for connecting steel bars and a profile steel framework in upper and lower prefabricated steel reinforced concrete columns into a whole; a pisolite type grouting material is used for pouring a connecting area of the upper and lower columns to form an assembly type integral structure column; the filament sleeves are arranged on the reinforcing steel bars at the two ends of the upper and lower prefabricated steel reinforced concrete columns and are in screwed connection with the reinforcing steel bars; and floor steel beams welded with the profile steel framework are arranged at the upper parts of the upper and lower prefabricated profile steel concrete columns. Compared with the prior art, the concrete filling and pouring method for connecting the upper column section and the lower column section of the prefabricated steel reinforced concrete column has the advantages that joint connection is moved to the middle of the column, beam-column joints with complex structures are avoided, construction quality and stress safety are guaranteed, factory production of the prefabricated steel reinforced concrete column is achieved, production efficiency is high, quality is more controllable, and the problem that an existing steel reinforced concrete column structure is difficult to construct on site is well solved.
Owner:ZHONGCHUAN NO 9 DESIGN & RES INST

Construction method of staggered assembled steel plate-rpc anti-blast door

The invention discloses a staggered splicing type steel plate-RPC anti-detonation door and a construction method thereof. According to the anti-detonation door, a cavity formed by a door leaf front side steel plate, a door leaf reverse side steel plate and a plurality of inner ribbed beams is filled with an RPC inner core. The construction method of the anti-detonation door comprises the steps that firstly, the door leaf front side steel plate, the door leaf reverse side steel plate and the inner ribbed beams are manufactured according to the size; secondly, the number of needed steel bars is calculated; thirdly, steel bar holes are formed in the inner ribbed beams in the length direction; fourthly, the door leaf front side steel plate is welded to the odd-number inner ribbed beams, and the door leaf reverse side steel plate is welded to the even-number inner ribbed beams; fifthly, the door leaf front side steel plate and the door leaf reverse side steel plate are spliced in a staggered manner, and the steel bars penetrate the steel bar holes; sixthly, reactive powder concrete is poured in the cavity formed by the door leaf front side steel plate, the door leaf reverse side steel plate and the multiple inner ribbed beams and is standing for 48 h; seventhly, the anti-detonation door is conveyed into a steam curing room at the temperature of 90 DEG C to be cured for 72 h; and eighthly, after 28 days, the RPC and the steel plates are effectively bonded to form the steel plate-RPC anti-detonation door. The staggered splicing type steel plate-RPC anti-detonation door and the construction method thereof are applied to anti-detonation protection projects.
Owner:HARBIN INST OF TECH
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products