Patents
Literature
Patsnap Copilot is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Patsnap Copilot

58results about How to "Avoid falling blocks" patented technology

Collapsible loess tunnel primary support arch replacement construction method

The invention provides a collapsible loess tunnel primary support arch replacement construction method. The method comprises the five steps of carrying out arch replacement construction preparation, temporary measures, soil body reinforcement, primary support steel arch frame pre-reinforcement and arch replacement construction. According to the construction method, a special lining construction rack does not need to be additionally arranged, operation is carried out based on a waterproof plate trolley, rapid construction is facilitated, and the cycle operation time is shortened. Soil body reinforcement and steel arch frame pre-reinforcement are brought into the construction procedure, the safety of operators can be guaranteed, the danger of soil body chipping or collapse in an arch frame dismantling process is effectively avoided, and meanwhile the bearing capacity, integrity and waterproof and anti-permeability performance of tunnel surrounding rock bodies are guaranteed. By adoptingthe arch replacement construction method for construction, the geological problems of collapsible loess tunnel arch crown settlement, peripheral convergence and the like can be effectively solved, thetunnel quality problems of secondary lining cracking, beyond limit and the like caused by large deformation of surrounding rock are prevented, the construction cost is effectively reduced, and the construction period is effectively shortened.
Owner:CHINA CONSTR SEVENTH ENG DIVISION CORP LTD +1

Preparation method of composite pantograph pan of electric locomotive

The invention discloses a preparation method of a composite pantograph pan of an electric locomotive. The preparation method comprises the following steps of (1), uniformly mixing silicon carbide powder, pitch coke powder and graphite powder, then adding molten high-temperature pitch, uniformly mixing at 130 to 150 DEG C, subsequently, cooling, and grinding a cooled mixture into powder with the granularity of 350 to 400 meshes, wherein the contents, in parts by weight, of the silicon carbide powder, the pitch coke powder, the graphite powder and the high-temperature pitch are 5 to 15 parts, 50to 60 parts, 5 to 10 parts and 25 to 30 parts respectively; (2), uniformly dispersing uniformly dispersed reduced graphene oxide dispersion liquid onto the powder obtained in the step (1) through spray drying; (3), predrying the powder obtained in the step (2), curing at 150 to 160 DEG C, enabling the cured powder to pass through a screw extruder, extruding to obtain a carbon pan blank of a required specification, roasting the carbon pan blank, and then discharging from a furnace, so that the composite pan is obtained. The preparation method provided by the invention is brief in process; a product is excellent in performance and good in self-lubricating property, further, does not damage a conducting wire, and is suitable to massively produce, and production equipment is simple.
Owner:SICHUAN UNIVERSITY OF SCIENCE AND ENGINEERING

Diffusion connection method between nickel-based high-temperature alloy ring-shaped piece and copper silver alloy

The invention provides a diffusion connection method between a nickel-based high-temperature alloy ring-shaped piece and a copper silver alloy. The method comprises the steps of preparation of a high-temperature alloy ring-shaped piece and a copper silver alloy ring-shaped piece, preparation and assembling of a sheath, hot isostatic pressure pretreatment, hot isostatic pressure process control, post-treatment and the like. According to the diffusion connection method between the nickel-based high-temperature alloy ring-shaped piece and the copper silver alloy, the hot isostatic pressure diffusion connection technology is adopted, the copper silver alloy is subjected to diffusion connection with the high-temperature alloy ring-shaped piece in a high-temperature high-pressure environment, and a connection piece for the high-temperature alloy ring-shaped piece and the copper silver alloy ring-shaped piece is formed. By means of the method, connection between the high-temperature alloy andthe copper silver alloy is well implemented, stripping, chip off-falling and layering of a connection layer and separation of the connection layer from a base body are avoided, the porosity of the connection layer is lowered, and good metallurgical bonding is realized.
Owner:BEIHANG UNIV

Bridge bearing structure passing through huge karst cave and construction method of bridge bearing structure

The invention relates to the field of tunnel and underground engineering, in particular to a bridge bearing structure passing through a huge karst cave and a construction method of the bridge bearingstructure. The bridge bearing structure comprises a bridge structure and a protection structure, the protection structure comprises a first supporting beam and a second supporting beam, and further comprises an open cut tunnel structure or a shed tunnel structure, the first supporting beam crosses the karst cave, the two ends of the first supporting beam are arranged on stable foundations on the two sides of the karst cave, the second supporting beam crosses the karst cave, the two ends of the second supporting beam are arranged on the stable foundations on the two sides of the karst cave, thetwo sides of the lower part of the open cut tunnel structure or the shed tunnel structure are fixed to the first supporting beam and the second supporting beam correspondingly, the bridge structure is arranged in the open cut tunnel structure or the shed tunnel structure and crosses the karst cave, and the two ends of the bridge structure are arranged the stable foundations on the two sides of the karst cave. The construction method is used for constructing the bridge bearing structure. Compared with a traditional method for crossing the karst cave through a backfilling method, the karst caveis continuously crossed through prestressed concrete, construction is convenient, the structure is reliable, and the defect of large settling after construction due to tunnel slag backfilling of thehuge karst cave is avoided.
Owner:CHINA RAILWAY ERYUAN ENG GRP CO LTD

Gas-bearing coal seams U-shaped well drilling and exploiting method

The invention provides a gas-bearing coal seams U-shaped well drilling and exploiting method, and the method comprises the steps of (1) drilling the straight well of the U-shaped well and conducting cavern completion; (2) drilling the straight well segment of the horizontal well; (3) drilling the horizontal segment of the horizontal well; and (4) perforating and fracturing the horizontal well so as to communicate a multilayer object layer of the gas-bearing coal seams. According to the invention, a non-target reservoir is deflected and the horizontal segment is drilled, like a sandstone or a limestone; a borehole is prevented from collapsing, block is prevented from falling off and the well is prevented from leaking when a target reservoir of gas-bearing coal seams is drilled; drilling efficiency is raised; drilling fluid is prevented from soaking the reservoir of the gas-bearing coal seams for a long time, particularly the coalbed gas layer and the shale gas layer; damage of particles in solid phase and drilling cuttings in the drilling fluid to the reservoir of the gas-bearing coal seams is effectively reduced; by communication between the horizontal segment of U-shaped well and the reservoir of the gas-bearing coal seams by pressing crack in a large scope, exploitation swept area and deflation area are increased; multilayer commingled production of the gas-bearing coal seams is realized; the utilization rate of the gas-bearing coal seams is raised; area well drilling quantity and total cost of well drilling are reduced; and the yield of a single well, exploitation degree and economic benefit are greatly increased.
Owner:贵州省地质矿产勘查开发局一一五地质大队 +1

Powder metallurgy friction body and manufacturing method thereof, powder metallurgy brake pad

The invention discloses a powder metallurgy friction body and a manufacturing method thereof, and a powder metallurgy brake pad. The powder metallurgy brake pad has relatively strong wear-resisting performance, can solve the phenomena of dreg falling, chip falling and entire friction material fall-off of an existing friction body in the process of vehicle braking, and thereby improves the servicelife of the friction body. The powder metallurgy friction body comprises a friction material layer which is composed of a substrate element, a lubricating element and a friction element, and a skeleton bonding material layer which is used for bonding the friction material layer and a friction body skeleton; the substrate element comprises bronze powder, reduced iron powder, manganese-iron alloy powder and nano molybdenum trioxide; the lubricating element comprises zinc sulfide and crystalline flake graphite; the friction element comprises titanium dioxide, zirconium oxide, feldspar and zirconsand; and the skeleton bonding material layer comprises bronze powder, reduced iron powder, manganese powder, molybdenum powder and tin powder. The powder metallurgy friction body can manufacture thepowder metallurgy brake pad and the powder metallurgy brake pad is applied to the aspect of urban railway transportation.
Owner:北京浦然轨道交通科技股份有限公司 +1

Demolding method and device for end plate of side plate of bilateral pre-tensioned pre-stressed concrete track plate

The invention discloses a demolding device for an end plate of a side plate of a bilateral pre-tensioned pre-stressed concrete track plate. The demolding device comprises a side plate demolding device and an end plate demolding device which are used separately or together, and a control system, wherein the side plate demolding device and the end plate demolding device are provided with driving mechanisms which are connected with the control system respectively; and the side plate demolding device and the end plate demolding device work simultaneously or in sequence under the control of the control system, so that the side plate and/or the end plate is separated from the track plate at one time. The invention further relates to a demolding method for the end plate of the side plate of the bilateral pre-tensioned pre-stressed concrete track plate using the demolding device. Preferably, the side plate demolding device and the end plate demolding device are arranged integrally into an integral side plate and end plate demolding device, so that the side plate and the end plate can be separated conveniently and efficiently in sequence or simultaneously. According to the demolding method and the demolding device, the side plate and/or the end plate can be separated conveniently and reliably at one time, so that the appearance of a product is ensured, and the production efficiency is increased.
Owner:欧阳炎

Construction Method of Reversed Slope Tunnel

The invention discloses a construction method of a reverse slope tunnel, which comprises the following steps: an arc-shaped heading is excavated in a circular shape, a core soil is reserved, and a first step is excavated; two second steps and two third steps reserved on the left and right sides of the core soil are respectively excavated, and the shotcrete and anchor support is carried out; the reserved core soil is excavated; an inverted arch is excavated and the initial support of the inverted arch is made; a waterproofing plate of the inverted arch is laid, and the side wall concrete is poured; after the pouring of the inverted arch concrete is completed, the inverted arch shall be backfilled in time, and the construction of secondary lining of the concrete shall be carried out. According to the invention, the construction of the reverse slope tunnel under the water level line of the adjacent reservoir is carried out, and the reverse slope is being made positive, so that the water seepage and the water inflow of the first step and the second step tunnel face can be timely discharged to the temporary water collecting pit of a third step to prevent the tunnel surrounding rock fromfalling out of the block, roof falling, landsliding or water inflowing. The integrity of the tunnel surrounding rock can be ensured, and the adverse effect on the reservoir and the surrounding environment can be reduced.
Owner:CHINA COMM NORTH ROAD & BRIDGE

Method and device for treating tunnel secondary lining vault cavity and local loose part

The invention belongs to a method and a device for treating a tunnel secondary lining vault cavity and a local loose part, and the device is characterized in that three slurry outlet holes with the diameter of 4mm are drilled in the positions of 90 degrees, 180 degrees and 270 degrees every 20cm on the pipe wall of a longitudinal grouting pipe, and the outer side of each slurry outlet hole is sealed by a PE (Polyethylene) film. Two exhaust holes with the diameter of 4 mm are drilled in the pipe wall of the longitudinal exhaust pipe at the 45-degree position and the 315-degree position every 20 cm, the outer side of each exhaust hole is sealed through a PE film, and the length of the longitudinal grouting pipe and the length of the longitudinal exhaust pipe are larger than that of a tunnel second lining pouring construction section. The longitudinal grouting pipes in the vertical pipes are communicated. According to the method, when the secondary lining concrete is finally set, the secondary lining concrete poured by the secondary lining is subjected to hole filling treatment grouting through the longitudinal grouting pipe, so that the integrity of the secondary lining concrete and grouting treatment slurry is improved, various concrete defects are repaired, a waterproof plate of a vault can be effectively prevented from being perforated and falling off, and the construction quality is guaranteed.
Owner:NO 1 ENG CO LTD OF FHEC OF CCCC

Reverse slope tunnel construction method

The invention discloses a construction method of a reverse slope tunnel, which comprises the following steps: an arc-shaped heading is excavated in a circular shape, a core soil is reserved, and a first step is excavated; two second steps and two third steps reserved on the left and right sides of the core soil are respectively excavated, and the shotcrete and anchor support is carried out; the reserved core soil is excavated; an inverted arch is excavated and the initial support of the inverted arch is made; a waterproofing plate of the inverted arch is laid, and the side wall concrete is poured; after the pouring of the inverted arch concrete is completed, the inverted arch shall be backfilled in time, and the construction of secondary lining of the concrete shall be carried out. According to the invention, the construction of the reverse slope tunnel under the water level line of the adjacent reservoir is carried out, and the reverse slope is being made positive, so that the water seepage and the water inflow of the first step and the second step tunnel face can be timely discharged to the temporary water collecting pit of a third step to prevent the tunnel surrounding rock fromfalling out of the block, roof falling, landsliding or water inflowing. The integrity of the tunnel surrounding rock can be ensured, and the adverse effect on the reservoir and the surrounding environment can be reduced.
Owner:CHINA COMM NORTH ROAD & BRIDGE

Segmented blasting hole excavation construction method for reconstruction and expansion of tunnel through karst landform water conservancy extra-small section

The invention discloses a segmented blasting hole excavation construction method for reconstruction and expansion of a tunnel through a karst landform water conservancy extra-small section. The segmented blasting hole excavation construction method is used for reconstruction and expansion of an original tunnel. The original tunnel is the extra-small section, and the excavation section is designedto be in a city door hole type. The segmented blasting hole excavation construction method comprises the following steps that S1, on-site reconnaissance and investigation are conducted on surroundingrock of the original tunnel, the existing state of the surrounding rock is actually mastered, and the category classification of the surrounding rock is confirmed to be IV or V; S2, advanced reinforcement is conducted on the existing state of the existing surrounding rock found through investigation in the step S1; and S3, classified blasting and segmented blasting of the same tunnel face are conducted on excavated different surrounding rock tunnel faces. A segmented blasting method in the step S3 comprises the steps that firstly, the top part of the original tunnel is excavated through blasting, and then a side wall and an inverted arch are excavated through blasting; or the position of the side wall is blasted firstly, and then the position of an arch crown is detonated. The segmented blasting hole excavation construction method has the characteristics of being safe, reliable, easy to construct and operate, remarkable in economic benefit and the like, can be widely applied to the field of water conservancy, mine and underground engineering widening construction, and is wide in application and popularization prospect.
Owner:中铁贵州工程有限公司

Method for connecting nickel-based high-temperature alloy annular piece with copper-silver alloy through partial diffusion bonding

The invention provides a method for connecting a nickel-based high-temperature alloy annular piece with copper-silver alloy through partial diffusion bonding. The method comprises the steps of nickel-based high-temperature alloy and copper-silver alloy preparation, package sheath preparation, assembling, hot isostatic pressure pretreatment, hot isostatic pressure process control, after-treatment and the like. The method for connecting the nickel-based high-temperature alloy annular piece with the copper-silver alloy through partial diffusion bonding adopts the hot isostatic pressure diffusionbonding technology, the copper-silver alloy is subjected to partial diffusion bonding with the nickel-based high-temperature alloy annular piece under the high-temperature high-pressure environment, and a partial connection annular piece of the nickel-based high-temperature alloy is formed. The method well achieves connecting of the nickel-based high-temperature alloy and the copper-silver alloy,connection layer disengagement, chip off-falling, and layering are avoided, the situation that the connection layer is separated from the substrate is avoided, the porosity of the connection layer isreduced, and good metallurgical bonding is achieved.
Owner:BEIHANG UNIV

Sequential supporting structure system of soil vertical shaft and construction method

The invention discloses a sequential supporting structure system of a soil vertical shaft and a construction method. The sequential supporting structure system of the soil vertical shaft and the construction method are reliable in technical scheme, simple in construction, low in investment and capable of effectively realizing safe and efficient excavation of a large-section soil vertical shaft. The structure system comprises a vertical shaft wall, a forepoling structure, a construction period supporting structure and a reinforced concrete shaft wall structure; the forepoling structure comprises a plurality of grouting steel pipe piles arranged around the outer side of the vertical shaft wall; the construction period supporting structure comprises a reinforcing mesh, profile steel walling cribs, supporting anchor rods and a concrete spraying layer, the reinforcing mesh is laid on the inner wall face of the vertical shaft wall, the plurality of profile steel walling cribs are evenly arranged on the inner side of the vertical shaft wall in the longitudinal direction, and the supporting anchor rods are evenly arranged in the longitudinal direction and the circumferential direction of the vertical shaft wall; the inner wall face of the vertical shaft wall is provided with the concrete spraying layer which enables the closed reinforcing mesh, the profile steel walling cribs and the supporting anchor rods to form a whole; and the reinforced concrete shaft wall structure is poured on the inner side face of the concrete spraying layer.
Owner:POWERCHINA HUADONG ENG COPORATION LTD

Thermal spraying combined manufacturing process of lost foam cast ductile iron pipe fittings

The invention discloses a thermal spraying combined manufacturing process of lost foam cast ductile iron pipe fittings. The thermal spraying combined manufacturing process comprises the following steps that a, lost foam is manufactured, specifically, foamed plastic is manufactured into real molds corresponding to the ductile iron pipe fittings in part structure and size; b, coating brushing is conducted, specifically, the real molds are assembled, combined and dried, the combined real molds are brushed with high-temperature preventing coating, and then the coating of the real molds is dried; c, thermal spraying treatment is conducted, specifically, the surface layer of the coating is subjected to thermal spraying treatment, the thermal spraying temperature is 50-250 DEG C, and the thickness of a thermal spraying material is no more than 1 mm; d, burying-in-box and modeling are conducted, specifically, the real molds subjected to thermal spraying operation are buried in a sand box and modeled; and e, casting and clearing are conducted, specifically, molten metal is poured into the sand box at the negative pressure, cooling, shot blasting, polishing clearing and a pressure test are conducted, and then finished products are obtained. The strength and flatness of a coating layer are improved through combination of thermal spraying, and the problem that the coating is likely to falloff, brushing is nonuniform, and consequently, the quality of the finished products is affected is well solved.
Owner:SICHUAN CHUANJIAN PIPES

Continuous casting tundish protecting technology

The invention discloses a continuous casting tundish protecting technology and relates to the field of steelmaking technologies. The continuous casting tundish protecting technology comprises the following steps that a, a tundish is baked at a baking position and moved to a pouring position after being baked; b, a protecting sleeve immersed into molten steel in a crystallizer is mounted at a tundish sliding water gap in the lower end of the tundish; c, the molten steel is poured into the tundish through a ladle; and d, the molten steel in the tundish is poured into the crystallizer by the protecting sleeve. The protecting sleeve is replaced on time, when the protecting sleeve is replaced, the liquid level of the molten steel in the crystallizer is lowered through manual operation of a casting speed disc, and after the protecting sleeve is replaced, the liquid level of the molten steel in the crystallizer is heightened through manual operation of the casting speed disc. According to thecontinuous casting tundish protecting technology, the protecting sleeve is replaced in time, so that the phenomena of damage to the protecting sleeve and fracturing or falling blocks of the protecting sleeve due to long-time high-temperature pouring are avoided, the situation that the falling blocks and the like at the protecting sleeve fall into the crystallizer is avoided, and slag inclusion ina continuous cast billet in the continuous casting tundish protecting technological process is avoided.
Owner:XINXING DUCTILE IRON PIPES CO LTD

Underwater non-blasting demolition construction method for reserved rock bank

InactiveCN111997008ALittle controllabilityLow geological requirementsWater-power plantsHydro energy generationSlagArchitectural engineering
The invention relates to the technical field of water conservancy and hydropower engineering tunnel construction, in particular to an underwater non-blasting demolition construction method for a reserved rock bank. The method comprises the steps that 1, after tunnel construction is completed, a tunnel inlet gate is closed, and a tunnel inlet vertical shaft is filled with horizontal pressure; 2, anadaptive long-arm excavator is selected according to the construction water depth, and a milling and excavating head is assembled at the end of a movable arm of the long-arm excavator; 3, an overwater construction platform used for bearing the long-arm excavator is built on the water surface according to the weight of the long-arm excavator; 4, the long-arm excavator is driven into the overwaterconstruction platform, and the milling and excavating head is controlled to dismantle the rock bank of the excavated part; and 5, after the rock bank is dismantled, the milling and excavating head isreplaced with a grab bucket, and slag materials are grabbed to be matched with a barge to be discharged. Compared with an underwater rock bank or rock plug blasting construction method, the method hasthe advantages of small construction disturbance, low requirements on geological conditions of a tunnel inlet and high adaptability by building the overwater construction platform to cooperate with the milling and digging head and the grab bucket to demount the reserved rock bank.
Owner:CHANGJIANG SURVEY PLANNING DESIGN & RES

A preparation method of electric locomotive pantograph composite slide plate

The invention discloses a preparation method of a composite pantograph pan of an electric locomotive. The preparation method comprises the following steps of (1), uniformly mixing silicon carbide powder, pitch coke powder and graphite powder, then adding molten high-temperature pitch, uniformly mixing at 130 to 150 DEG C, subsequently, cooling, and grinding a cooled mixture into powder with the granularity of 350 to 400 meshes, wherein the contents, in parts by weight, of the silicon carbide powder, the pitch coke powder, the graphite powder and the high-temperature pitch are 5 to 15 parts, 50to 60 parts, 5 to 10 parts and 25 to 30 parts respectively; (2), uniformly dispersing uniformly dispersed reduced graphene oxide dispersion liquid onto the powder obtained in the step (1) through spray drying; (3), predrying the powder obtained in the step (2), curing at 150 to 160 DEG C, enabling the cured powder to pass through a screw extruder, extruding to obtain a carbon pan blank of a required specification, roasting the carbon pan blank, and then discharging from a furnace, so that the composite pan is obtained. The preparation method provided by the invention is brief in process; a product is excellent in performance and good in self-lubricating property, further, does not damage a conducting wire, and is suitable to massively produce, and production equipment is simple.
Owner:SICHUAN UNIVERSITY OF SCIENCE AND ENGINEERING
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products