The invention provides a combined dust
settling method for large-area excavation and explosion in a water conservancy and
hydropower project. The method comprises the following steps: 1) before
detonation, injecting water into blastholes; 2) installing a pressurized water pump and a plurality of groups of
high pressure spray gun; 3) arranging river-crossing water spraying pipes at the upper
stream and lower
stream of a riverway located in an explosion area; 4) spraying water to wet the ground of the explosion area before
detonation; 5) after
detonation, as water injected into the blastholes exerts an
inhibitory effect on produced
smoke, immediately starting the plurality of groups of
high pressure spray gun for water spraying so as to cover rising
smoke dust; and 6) opening the river-crossing water spraying pipes at the upper
stream and lower stream of the riverway to form a
water curtain so as to finish effective dust
settling of dust clouds produced during large-area excavation and explosion in the water conservancy and
hydropower project. The combined dust
settling method for large-area excavation and explosion in the water conservancy and
hydropower project can overcome problems of dust,
toxic gas and other harm caused by large-area open-air explosion in the water conservancy and hydropower project and is economic, environment-friendly, rapid and effective.