The invention relates to an incremental launching construction method for a box
culvert overcrossing a subway. The incremental launching construction method comprises the following steps that S101, a
supporting system is constructed, specifically, the
supporting system is constructed in front of the box
culvert and above an existing subway; in the pushing direction, a sliding plate is arranged at the bottom end of the initial position of the box
culvert, and the box culvert slides on the sliding plate; the soil body in front of the box culvert and above the existing subway is subjected to multiple times of grouting reinforcement; and S103, box culvert pushing construction is conducted, specifically, a counterweight
assembly is installed at the top end of the box culvert, and the installation position of the counterweight
assembly on the box culvert is adjusted along with pushing of the box culvert. According to the incremental launching construction method, the jacking direction of the box culvert can be limited through the high-pressure jet grouting piles and the supporting piles, and the box culvert is prevented from deviating in the incremental launching process; and
deep hole grouting reinforcement is carried out on soil bodies at the bottom ends of the multiple high-pressure jet grouting piles and the multiple supporting piles, and dense grouting reinforcement is carried out on weak stress positions of the soil bodies, so that the high-pressure jet grouting piles, the supporting piles and a grouting reinforcement area form a U-shaped structure reinforcement
system.