The invention discloses a method for managing and controlling progress by using three graphs and one curve, and relates to the technical field of
civil engineering, and the method comprises the steps: 1, carrying out the
spatial structure disassembly of a building, and forming a physical
spatial structure tree; 2, according to the
physical space structure correlation process model, generating a
data model of process + part +
engineering quantity budget; 3, generating a
construction plan according to project time arrangement, and automatically generating a
Gantt chart of a building level, a network diagram of a batch level, a matrix diagram of the building level and an image progress curve of the building level; step 4, through
process behavior management of acceptance, manual feedback, quantity-price conversion and the like, driving a
Gantt chart, a network diagram, a matrix diagram and an image progress curve, and carrying out project progress management; through structural disassembly,
data association and automatic generation of a style chart, and through
information acquisition,
processing and sharing in a
construction management process, the problems of high difficulty and cost of compiling, maintenance and sharing of three graphs and one curve and information synchronization
hysteresis quality are solved.