This invention relates to the field of construction
elevator foundation construction technology, aiming to solve the problems of material waste caused by existing technologies that separately set the construction
elevator foundation on the
basement roof slab or set it on the
basement floor slab through the roof slab. This invention provides a construction
elevator foundation construction method based on the settlement of the
basement foundation slab, including the following steps: Step 1: Determine the installation point of the construction elevator; Step 2: Settle the basement foundation slab at the selected installation point, construct a
cushion layer on the base layer, and then construct a waterproof structural layer on the surface of the
cushion layer; Step 3: Tie the reinforcement of the basement foundation slab; Step 4: Pre-embed drainage pipes; Step 5: Pour concrete for the basement foundation slab, using the basement foundation slab in the settlement space as the construction elevator foundation; Step 6: Install and inspect the construction elevator; Step 7: Dismantle the construction elevator; Step 8: Backfill the settlement pit formed between the construction elevator foundation and the basement foundation slab outside the settlement space.