The invention discloses a
tunnel construction method for a side span non-filling type long and narrow shallow-bottom
karst cave section, and relates to the field of underground
engineering. The invention aims to provide a construction method for the side span
karst cave section of a tunnel under the specific geological condition of a non-filling type long and narrow shallow-bottom
karst cave. According to the technical scheme, the
tunnel construction method for the side span non-filling type long and narrow shallow-bottom karst cave section comprises the steps that a karst cave cavity in the lower portion of a tunnel excavation face is backfilled with cave
slag, a karst cave opening is reinforced after danger is eliminated, a tunnel arch outside the karst cave cavity is subjected to advance support, tunnel excavation is conducted in a segmented circulating excavation mode, steel frames are erected along the tunnel arch and the whole section of a side wall, the tunnel arch and the sidewall are supported through anchor rods of a construction
system, surrounding rock around the karst cave wall at the bottom of the tunnel is reinforced, a
reinforced concrete slab at the bottom of thetunnel is constructed, a karst cave drainage
pipe is constructed, the tunnel side karst cave is backfilled with concrete, and finally a tunnel secondary
reinforced concrete lining and a
road surface are constructed. The
tunnel construction method is suitable for the design and construction of the side span non-filling type long and narrow shallow-bottom karst cave section.