The present application relates to a kind of sinter cooling
waste gas waste heat cascade utilization
system and use method, including ring cooling
machine, sealed upper cover, wind box and
waste gas circulation
system,
waste gas circulation
system includes
waste heat boiler, regulating valve and
diffusion valve, normal production state, all accident
diffusion valves are in
closed state, the waste gas of upper cover section and upper cover second section is imported into
waste heat boiler, after heat exchange by regenerative fan I is sent into back wind second section wind box and back wind third section wind box;When waste heat boiler import wind temperature is high, waste heat boiler import wind temperature is adjusted by regulating valve and accident
diffusion valve;The waste gas of upper cover third section is sent into
sintering machine material surface or back wind first section wind box, the waste gas of upper cover fourth section is sent into back wind first section wind box or is discharged after purification by dust removal system, the waste gas of upper cover fifth section is sent into back wind fourth section wind box by regenerative fan IV.Its advantages are: effectively improve the
utilization rate and the stability of operation of waste heat boiler;Increase the proportion of waste gas self-circulation, realize ring cooling
machine waste gas
zero emission.