The invention discloses a tunnel collapse handling method for a convergent collapse cavity, and relates to the field of tunnel engineering. By the adoption of the tunnel collapse handling method for the convergent collapse cavity, the problem that an existing handling method lacks operability, can cause potential safety hazards, and is not economical is solved. According to the technical scheme, the tunnel collapse handling method for the convergent collapse cavity comprises the steps that first, after the tunnel collapse cavity is stabilized, a construction platform is formed by means of collapse residues; second, a landslide-affected section is divided into an excavated landslide-affected section and a non-excavated landslide-affected section which are separately reinforced; third, concrete is sprayed to support the collapse cavity; fourth, a temporary support and a formwork are constructed on a landslide section, a manhole is formed in the portion, in the middle of the landslide section, of a tunnel vault, the collapse cavity is backfilled with concrete, landslide anchoring rods are constructed, reinforcement of the temporary support and the landslide-affected section is removed, and the construction platform is removed through excavation; and finally, a tunnel drain pipe and a waterproof plate are constructed according to original design, and secondary lining concrete is constructed. The tunnel collapse handling method has high practical value in handling convergent tunnel collapse cavities.